Based on reasonable assumptions that simplified the calculational model,a simple and practical method was proposed to calculate the post-construction settlement of high-speed railway bridge pile foundation by using th...Based on reasonable assumptions that simplified the calculational model,a simple and practical method was proposed to calculate the post-construction settlement of high-speed railway bridge pile foundation by using the Mesri creep model to describe the soil characteristics and the Mindlin-Geddes method considering pile diameter to calculate the vertical additional stress of pile bottom.A program named CPPS was designed for this method to calculate the post-construction settlement of a high-speed railway bridge pile foundation.The result indicates that the post-construction settlement in 100 years meets the requirements of the engineering specifications,and in the first two decades,the post-construction settlement is about 80% of its total settlement,while the settlement in the rest eighty years tends to be stable.Compared with the measured settlement after laying railway tracks,the calculational result is closed to that of the measured,and the results are conservative with a high computational accuracy.It is noted that the method can be used to calculate the post-construction settlement for the preliminary design of high-speed railway bridge pile foundation.展开更多
In order to eliminate the settlement underestimation in surcharge preload engineering, a study based on Bjerrum's creep diagram and the tangent slope definition of secondary consolidation coefficient was carried o...In order to eliminate the settlement underestimation in surcharge preload engineering, a study based on Bjerrum's creep diagram and the tangent slope definition of secondary consolidation coefficient was carried out to analyze the time effect of secondary consolidation coefficient of over consolidated soil, and a time–growth model for it was formulated. As Bjerrum's creep diagram is an idealized model, oedometer tests were performed to improve the above time–growth model of secondary consolidation coefficient for the purpose of achieving a better agreement with the actual ground situations. It is found that secondary consolidation coefficient of over consolidated soil not only decreases with the ratio of historical maximum to current effective stress of soil(OCR), but also increases with the development time of secondary consolidation. No matter how large OCR is, the long-term time effect of secondary consolidation coefficient of over consolidated soil is all significant. Based on the above results, a model for settlement estimation was formulated and a case study to estimate it indicates that the settlement estimated by our method is 2–5 times larger than that estimated by the previous method. Moreover, the larger the OCR is as well as the longer the service life is, the larger the difference between our method and the previous method is. Thus, the post-construction secondary settlement in surcharge preload engineering will be underestimated when neglecting the time effect of secondary consolidation coefficient in over consolidated state.展开更多
A case of Qinghuayuan tunnel excavation below the existing Beijing Subway Line 10 is presented.The new Qinghuayuan tunnel,part of the Beijing-Zhangjiakou High-speed Railway,was excavated by a shield machine with an ou...A case of Qinghuayuan tunnel excavation below the existing Beijing Subway Line 10 is presented.The new Qinghuayuan tunnel,part of the Beijing-Zhangjiakou High-speed Railway,was excavated by a shield machine with an outer diameter of 12.2 m.The existing subway was excavated by shallow tunnelling method.The project layout,geological conditions,reinforcement measures,operational parameters of shield machine and monitoring results of the project are introduced.During the Qinghuayuan tunnel excavation below the existing subway,total thrust,shield driving speed,cutterhead rotation speed and torque were manually controlled below the average values obtained from the previous monitoring of this project,which could effectively reduce the disturbance of the surrounding soil induced by shield excavation.The Gaussian fitting function can appropriately fit both the ground and the existing subway settlements.The trough width is influenced not only by the excavation overburden depth,but also by the forepoling reinforcement and tail void grouting measures.展开更多
Foundation settlement is of great significance for high-fill engineering in collapsible loess areas.To predict the construction settlement of Lüliang Airport located in Shanxi Province,China,a plane strain finite...Foundation settlement is of great significance for high-fill engineering in collapsible loess areas.To predict the construction settlement of Lüliang Airport located in Shanxi Province,China,a plane strain finite element method considering the linear variation in the modulus,was carried out in this paper based on the results of geotechnical tests.The stress and deformation of four typical sections caused by layered fill are simulated,and then the settlement of the high-fill airport is calculated and analyzed by inputting three sets of parameters.The relative soft parameters of loess geomaterials produce more settlement than the relatively hard parameters.The thicker the filling body is,the greater the settlement is.The filling body constrained by mountains on both sides produces less settlement than the filling body constrained by a mountain on only one side even the filling thickness is almost the same.The settlement caused by the original subbase accounts for 56%−77%of the total settlement,while the fill soils themselves accounts for 23%−44%of the total settlement,which is approximately consistent with the field monitoring results.It provides a good reference for predicting the settlement of similar high-fill engineering.展开更多
A simplified approach is presented for the analysis of the settlement of vertically loaded pile groups. In order to simulate the nonlinear pile-to-pile interaction in pile groups, the soils along the piles are assumed...A simplified approach is presented for the analysis of the settlement of vertically loaded pile groups. In order to simulate the nonlinear pile-to-pile interaction in pile groups, the soils along the piles are assumed to behave as a series of nonlinear springs subjected to the shaft shear stress at the pile/soil interface. Considering the displacement reduction induced by the pile-to-pile interaction, the shear-deformation method is adopted to approximate the displacement field of the layered soils around the piles, and the equivalent stiffness of the springs is obtained. Furthermore, the load-settlement response of pile groups is deduced by modifying the load-transfer functions to account for the pile-to-pile interaction. The settlements of a laboratory pile groups computed by the presented approach are in a good agreement with measured results. The analysis on Contrastive parameters shows that the settlements of pile group decrease with the increase of the pile space and pile length, and the part of piles exceeding the critical pile length has little contribution to the beating capacity of the pile groups.展开更多
The calculation of residual settlement of bidirectional reinforced composite foundation, which is composed of geocell cushion over gravel piles, was studied. The geocell cushion was modeled as a thin flexible plate wi...The calculation of residual settlement of bidirectional reinforced composite foundation, which is composed of geocell cushion over gravel piles, was studied. The geocell cushion was modeled as a thin flexible plate with large deflection. Based on the Kirchhoff hypothesis, the governing differential equations and boundary conditions of the deformation of geocell cushion under working load were founded using von Karman method and solved by Galerkin method. On theses bases, the gravel piles and inter-pile soils were assumed as Winkler ground with variable spring stiffness so as to execute the approximate calculation of the residual settlement of the bidirectional reinforced composite foundation. The calculation method was verified by two laboratory experiments concerning settlement of embankments. One experiment was with just geocell cushion installed to treat the soft clay under embankments; another one was with both geocell cushion and gravel piles installed. The results show that the calculated settlement curve and the maximum settlement are closed to the observed ones.展开更多
A new technique for the analysis of the three-dimensional collapse failure mechanism and the ground surface settlements for the large-diameter shield tunnels were presented.The technique is based on a velocity field m...A new technique for the analysis of the three-dimensional collapse failure mechanism and the ground surface settlements for the large-diameter shield tunnels were presented.The technique is based on a velocity field model using more different truncated solid conical blocks to clarify the multiblock failure mechanism.Furthermore,the shape of blocks between the failure surface and the tunnel face was considered as an entire circle,and the supporting pressure was assumed as non-uniform distribution on the tunnel face and increased with the tunnel embedded depth.The ground surface settlements and failure mechanism above large-diameter shield tunnels were also investigated under different supporting pressures by the finite difference method.展开更多
In order to analyze the effects of backfill materials, geometries and slab setting on the settlement of bridge approach embankment, scale model was built based on the structural characteristics of bridge approach emba...In order to analyze the effects of backfill materials, geometries and slab setting on the settlement of bridge approach embankment, scale model was built based on the structural characteristics of bridge approach embankment, and scale model tests were carried out under different conditions. The results show that when graded gravels were selected as the backfill materials, the effect of setting approach slab to reduce the differential settlement is more prominent. When lime soils were selected as the backfill material, approach slab can moderate the longitudinal settlement slope. When using different backfill materials, the ultimate settlement of the positive trapezoidal backfill geometries is less than that of the inverted trapezoid, and the backfill geometries have little effect on the settlement slope.展开更多
Top structure and basement will confront the risk of being damaged on account of large stress and strain fields incurred by differential uplift and settlement between inner column and diaphragm wall in top-down method...Top structure and basement will confront the risk of being damaged on account of large stress and strain fields incurred by differential uplift and settlement between inner column and diaphragm wall in top-down method. Top-down excavation of the Metro Line 10 in Shanghai was modeled with finite element analysis software ABAQUS and parameters of subsoil were obtained by inverse analysis. Based on the finite element model and parameters, changes in the following factors were made to find more effective methods to restrain differential uplift and settlement: length of diaphragm wall, thickness of jet-grouting reinforcement layer, ways of subsoil reinforcement, sequence of pit excavation, connection between slabs and diaphragm wall or column and width of pit. Several significant results are acquired. The longer the diaphragm wall is, the greater the differential uplift between column and diaphragm wall is. Rigidity of roof slab is in general not strong enough to keep diaphragm wall and column undergoing the same uplift during excavation; Uplift at head of column and differential uplift between column and diaphragm wall decrease when subsoil from-16.6 to-43 m in pit is reinforced through jet-grouting. But, as excavation proceeds to a lower level, benefit from soil reinforcement diminishes. During the process applying vertical load, the larger the depth of diaphragm wall is, the smaller the settlement is at head of column and diaphragm wall, and the greater the differential settlement is between column and diaphragm wall. When friction connection is implemented between column, diaphragm wall and floor slabs, uplifts at head of column and diaphragm wall are larger than those of the case when tie connection is implemented, and so does differential uplift between column and diaphragm wall. The maximum deflection of diaphragm wall decreases by 58% on account of soil reinforcement in pit. The maximum deflection of diaphragm wall decreases by 61.2% when friction connection is implemented instead of tie connection.展开更多
A new approach is proposed to analyze the settlement behavior for single pile embedded in layered soils. Firstly, soil layers surrounding pile shaft are simulated by using distributed Voigt model, and finite soil laye...A new approach is proposed to analyze the settlement behavior for single pile embedded in layered soils. Firstly, soil layers surrounding pile shaft are simulated by using distributed Voigt model, and finite soil layers under the pile end are assumed to be virtual soil-pile whose cross-section area is the same as that of the pile shaft. Then, by means of Laplace transform and impedance function transfer method to solve the static equilibrium equation of pile, the analytical solution of the displacement impedance fimction at the pile head is derived. Furthermore, the analytical solution of the settlement at the head of single pile is theoretically derived by virtue of convolution theorem. Based on these solutions, the influences of parameters of soil-pile system on the settlement behavior for single pile are analyzed. Also, comparison of the load-settlement response for two well-instrumented field tests in multilayered soils is given to demonstrate the effectiveness and accuracy of the proposed approach. It can be noted that the presented solution can be used to calculate the settlement of single pile for the preliminary design of pile foundation.展开更多
The purpose of this work is to predict the state of collapse in shallow tunnel in layered strata by using a new curved failure mechanism within the framework of upper bound theorem.Particular emphasis is first given t...The purpose of this work is to predict the state of collapse in shallow tunnel in layered strata by using a new curved failure mechanism within the framework of upper bound theorem.Particular emphasis is first given to consider the effects of seepage forces and surface settlement.Furthermore,the Hoek-Brown nonlinear failure criterion is adopted to analyze the influence of different factors on the collapsing shape.Two different curve functions which describe two different rock layers are obtained by virtual work equations under the variational principle.According to the numerical results,the parameter B in Hoek-Brown failure criterion and the unit weights in different rock layers have a positive relationship with the size of collapsing block while pore pressure coefficient and the parameter A in Hoek-Brown failure criterion present a reverse tend.展开更多
The process and characteristics of loading on high-speed railway bridge pile foundation were firstly obtained by means of field research and analysis,and the corresponding loading function was presented.One-dimensiona...The process and characteristics of loading on high-speed railway bridge pile foundation were firstly obtained by means of field research and analysis,and the corresponding loading function was presented.One-dimensional consolidation equation of elastic multilayered soils was then established with single drainage or double drainages under multilevel loading.Moreover,the formulas for calculating effective stress and settlement were derived from the Laplace numerical inversion transform.The three-dimensional composite analysis method of bridge pile group was improved,where the actual load conditions of pile foundation could be simulated,and the consolidation characteristics of soil layers beneath pile were also taken into account.Eventually,a corresponding program named LTPGS was developed to improve the calculation efficiency.The comparison between long-term settlement obtained from the proposed method and the in-situ measurements of pile foundation was illustrated,and a close agreement is obtained.The error between computed and measured results is less than 1 mm,and it gradually reduces with time.It is shown that the proposed method can effectively simulate the long-term settlement of pile foundation and program LTPGS can provide a reliable estimation.展开更多
The proliferation of Hoek-Brown nonlinear failure criterion and upper bound theorem makes it possible to evaluate the stability of circular tunnels with an original curved collapsing mechanism. The arch effect of shal...The proliferation of Hoek-Brown nonlinear failure criterion and upper bound theorem makes it possible to evaluate the stability of circular tunnels with an original curved collapsing mechanism. The arch effect of shallow circle tunnel is not taken into consideration so that the mechanical characteristics can be easily described. Based on the mechanism, the upper bound solution of supporting pressure of tunnels under the condition of surface settlements and overloads on the ground surface is derived. The objective function is formed from virtual work equations under the variational principle, and solutions are presented by the optimum theory. Comparisons with previous works are made. The numerical results of the present method show great agreement with those of existing ones. With regard to the surface settlement and overloads, the influence of different rock parameters on the collapsing shape is analyzed.展开更多
The mechanism of long-short composite piled raft foundation was discussed. Assuming the relationship between shear stress and shear strain of the surrounding soil was elasto-plastic, shear displacement method was empl...The mechanism of long-short composite piled raft foundation was discussed. Assuming the relationship between shear stress and shear strain of the surrounding soil was elasto-plastic, shear displacement method was employed to establish the different explicit relational equations between the load and the displacement at the top of pile in either elastic or elasto-plastic period. Then Mylonakis & Gazetas model was introduced to simulate the interaction between two piles or between piles and soil. Considering the effect of cushion, the flexible coefficients of interaction were provided, With the addition of a relevant program, the settlement calculation for long-short composite piled raft foundation was developed which could be used to account for the interaction of piles, soil and cushion. Finally, the calculation method was used to analyze an engineering example. The calculated value of settlement is 10.2 ram, which is close to the observed value 8.8 mm.展开更多
Limit analysis of the stability of geomechanical projects is one of the most difficult problems.This work investigates the influences of different parameters in NL failure strength on possible collapsing block shapes ...Limit analysis of the stability of geomechanical projects is one of the most difficult problems.This work investigates the influences of different parameters in NL failure strength on possible collapsing block shapes of single and twin shallow tunnels with considering the effects of surface settlement.Upper bound solutions derived by functional catastrophe theory are used for describing the distinct characteristics of falling blocks of different parts in twin tunnels.Furthermore the analytical solutions of minimum supporting pressures in shallow tunnels are obtained by the help of the variational principle.Lastly,the comparisons are made both in collapsed mechanism and stability factor with different methods.According to the numerical results in this work,the influences of different parameters on the size of collapsing block are presented in the tables and the limit supporting loads are illustrated in the form graphs that account for the surface settlement.展开更多
In order to investigate the influence of complex conditions of in-situ surrounding rocks on the settlement behavior of nubbly coal mine waste subjected to high gravity pressure,four kinds of loading chambers made of d...In order to investigate the influence of complex conditions of in-situ surrounding rocks on the settlement behavior of nubbly coal mine waste subjected to high gravity pressure,four kinds of loading chambers made of different similar materials with different elastic moduli in experiments were used to simulate the deformation features of in-site rocks,including soft,moderate hardness,hard and extra-hard rocks. The results show that all the settlement-axial load (or axial strain-stress) curves obtained under four different surrounding rock conditions present power-exponential function feature. The final settlement of coal mine waste under the same axial load is closely related to the lumpiness gradations and the deformation behavior of chamber materials used to simulate behaviors of different in-situ surrounding rocks. In the same surrounding rock condition,the final settlement under the same maximum axial load decreases with the decrease of the proportion of larger gradation of coal mine waste. While for the same lumpiness gradation case,the settlement increases with the decrease of elastic modulus of simulated surrounding rocks and the lateral pressure induced by axial load increases with the increase of elastic modulus of loading chambers that are used to simulate different surrounding rocks. The test results also reveal that both the compaction curve and lateral pressure curve show a three-stage behavior,and the duration of each stage,which is closely related to gradations and the deformation feature of loading chamber materials,decreases with the increase of the proportion of the small size of coal mine waste and elastic modulus of the simulated rock materials.展开更多
This study aims to predict ground surface settlement due to shallow tunneling and introduce the most affecting parameters on this phenomenon.Based on data collected from Shanghai LRT Line 2 project undertaken by TBM-E...This study aims to predict ground surface settlement due to shallow tunneling and introduce the most affecting parameters on this phenomenon.Based on data collected from Shanghai LRT Line 2 project undertaken by TBM-EPB method,this research has considered the tunnel's geometric,strength,and operational factors as the dependent variables.At first,multiple regression(MR) method was used to propose equations based on various parameters.The results indicated the dependency of surface settlement on many parameters so that the interactions among different parameters make it impossible to use MR method as it leads to equations of poor accuracy.As such,adaptive neuro-fuzzy inference system(ANFIS),was used to evaluate its capabilities in terms of predicting surface settlement.Among generated ANFIS models,the model with all input parameters considered produced the best prediction,so as its associated R^2 in the test phase was obtained to be 0.957.The equations and models in which operational factors were taken into consideration gave better prediction results indicating larger relative effect of such factors.For sensitivity analysis of ANFIS model,cosine amplitude method(CAM) was employed; among other dependent variables,fill factor of grouting(n) and grouting pressure(P) were identified as the most affecting parameters.展开更多
An analysis of the stability of large-diameter circular tunnels and ground settlement during tunnelling by a pressurized shield was presented. An innovative three-dimensional translational multi-block failure mechanis...An analysis of the stability of large-diameter circular tunnels and ground settlement during tunnelling by a pressurized shield was presented. An innovative three-dimensional translational multi-block failure mechanism was proposed to determine the face support pressure of large-shield tunnelling. Compared with the currently available mechanisms, the proposed mechanism has two unique features:(1) the supporting pressure applied to the tunnel face is assumed to have a non-uniform rather than uniform distribution, and(2) the method takes into account the entire circular excavation face instead of merely an inscribed ellipse. Based on the discrete element method, a numerical simulation of the Shanghai Yangtze River Tunnel was carried out using the Particle Flow Code in two dimensions. The immediate ground movement during excavation, as well as the behaviour of the excavation face, the shield movement, and the excavated area, was considered before modelling the excavation process.展开更多
A new measurement technique is used to determine the settlement of bridge pile foundation and the thickness of deep compressed soft layer. The finite element Plaxis 3D foundation program is used in the analysis with a...A new measurement technique is used to determine the settlement of bridge pile foundation and the thickness of deep compressed soft layer. The finite element Plaxis 3D foundation program is used in the analysis with a proposed empirical equation to modify the input parameters represented by the soil compression modulus. The results of the numerical analysis using the proposed empirical equation provide insight to the settlement analysis of pile groups in soft clayey soils; consequently, the finite element Plaxis 3D program can be a useful tool for numerical analysis. The numerical analysis is modified by adjusting the calculation of compression modulus from those obtained under pressure between 100-200 kPa by which the results of the settlement are modified and thus matching the realistic measurements. The absolute error is 3 mm which is accepted compared with the last researches. This scenario can be applied for the similar problems in the theoretical applications of deep foundations.展开更多
基金Projects(2009G008-B,2010G018-E-3) supported by Key Projects of China Railway Ministry Science and Technology Research and Development ProgramProject(CX2013B076) supported by Hunan Provincial Innovation Foundation For Postgraduate,China
文摘Based on reasonable assumptions that simplified the calculational model,a simple and practical method was proposed to calculate the post-construction settlement of high-speed railway bridge pile foundation by using the Mesri creep model to describe the soil characteristics and the Mindlin-Geddes method considering pile diameter to calculate the vertical additional stress of pile bottom.A program named CPPS was designed for this method to calculate the post-construction settlement of a high-speed railway bridge pile foundation.The result indicates that the post-construction settlement in 100 years meets the requirements of the engineering specifications,and in the first two decades,the post-construction settlement is about 80% of its total settlement,while the settlement in the rest eighty years tends to be stable.Compared with the measured settlement after laying railway tracks,the calculational result is closed to that of the measured,and the results are conservative with a high computational accuracy.It is noted that the method can be used to calculate the post-construction settlement for the preliminary design of high-speed railway bridge pile foundation.
基金Project(51178419)supported by the National Natural Science Foundation of China
文摘In order to eliminate the settlement underestimation in surcharge preload engineering, a study based on Bjerrum's creep diagram and the tangent slope definition of secondary consolidation coefficient was carried out to analyze the time effect of secondary consolidation coefficient of over consolidated soil, and a time–growth model for it was formulated. As Bjerrum's creep diagram is an idealized model, oedometer tests were performed to improve the above time–growth model of secondary consolidation coefficient for the purpose of achieving a better agreement with the actual ground situations. It is found that secondary consolidation coefficient of over consolidated soil not only decreases with the ratio of historical maximum to current effective stress of soil(OCR), but also increases with the development time of secondary consolidation. No matter how large OCR is, the long-term time effect of secondary consolidation coefficient of over consolidated soil is all significant. Based on the above results, a model for settlement estimation was formulated and a case study to estimate it indicates that the settlement estimated by our method is 2–5 times larger than that estimated by the previous method. Moreover, the larger the OCR is as well as the longer the service life is, the larger the difference between our method and the previous method is. Thus, the post-construction secondary settlement in surcharge preload engineering will be underestimated when neglecting the time effect of secondary consolidation coefficient in over consolidated state.
基金Project(U1934210)supported by the Key Project of High-speed Rail Joint Fund of National Natural Science Foundation of ChinaProject(8202037)supported by the Natural Science Foundation of Beijing,China。
文摘A case of Qinghuayuan tunnel excavation below the existing Beijing Subway Line 10 is presented.The new Qinghuayuan tunnel,part of the Beijing-Zhangjiakou High-speed Railway,was excavated by a shield machine with an outer diameter of 12.2 m.The existing subway was excavated by shallow tunnelling method.The project layout,geological conditions,reinforcement measures,operational parameters of shield machine and monitoring results of the project are introduced.During the Qinghuayuan tunnel excavation below the existing subway,total thrust,shield driving speed,cutterhead rotation speed and torque were manually controlled below the average values obtained from the previous monitoring of this project,which could effectively reduce the disturbance of the surrounding soil induced by shield excavation.The Gaussian fitting function can appropriately fit both the ground and the existing subway settlements.The trough width is influenced not only by the excavation overburden depth,but also by the forepoling reinforcement and tail void grouting measures.
基金Project(2020M670604)supported by the China Postdoctoral Science FoundationProject(41790434)supported by the National Natural Science Foundation of China。
文摘Foundation settlement is of great significance for high-fill engineering in collapsible loess areas.To predict the construction settlement of Lüliang Airport located in Shanxi Province,China,a plane strain finite element method considering the linear variation in the modulus,was carried out in this paper based on the results of geotechnical tests.The stress and deformation of four typical sections caused by layered fill are simulated,and then the settlement of the high-fill airport is calculated and analyzed by inputting three sets of parameters.The relative soft parameters of loess geomaterials produce more settlement than the relatively hard parameters.The thicker the filling body is,the greater the settlement is.The filling body constrained by mountains on both sides produces less settlement than the filling body constrained by a mountain on only one side even the filling thickness is almost the same.The settlement caused by the original subbase accounts for 56%−77%of the total settlement,while the fill soils themselves accounts for 23%−44%of the total settlement,which is approximately consistent with the field monitoring results.It provides a good reference for predicting the settlement of similar high-fill engineering.
基金Project(50708033) supported by the National Natural Science Foundation of ChinaProjects(200923, CXKJSF0108-2) supported by Transportation Technical Project of Hunan Province, China
文摘A simplified approach is presented for the analysis of the settlement of vertically loaded pile groups. In order to simulate the nonlinear pile-to-pile interaction in pile groups, the soils along the piles are assumed to behave as a series of nonlinear springs subjected to the shaft shear stress at the pile/soil interface. Considering the displacement reduction induced by the pile-to-pile interaction, the shear-deformation method is adopted to approximate the displacement field of the layered soils around the piles, and the equivalent stiffness of the springs is obtained. Furthermore, the load-settlement response of pile groups is deduced by modifying the load-transfer functions to account for the pile-to-pile interaction. The settlements of a laboratory pile groups computed by the presented approach are in a good agreement with measured results. The analysis on Contrastive parameters shows that the settlements of pile group decrease with the increase of the pile space and pile length, and the part of piles exceeding the critical pile length has little contribution to the beating capacity of the pile groups.
文摘The calculation of residual settlement of bidirectional reinforced composite foundation, which is composed of geocell cushion over gravel piles, was studied. The geocell cushion was modeled as a thin flexible plate with large deflection. Based on the Kirchhoff hypothesis, the governing differential equations and boundary conditions of the deformation of geocell cushion under working load were founded using von Karman method and solved by Galerkin method. On theses bases, the gravel piles and inter-pile soils were assumed as Winkler ground with variable spring stiffness so as to execute the approximate calculation of the residual settlement of the bidirectional reinforced composite foundation. The calculation method was verified by two laboratory experiments concerning settlement of embankments. One experiment was with just geocell cushion installed to treat the soft clay under embankments; another one was with both geocell cushion and gravel piles installed. The results show that the calculated settlement curve and the maximum settlement are closed to the observed ones.
基金Project(41202220) supported by the National Natural Science Foundation of ChinaProject(2011YYL034) supported by the Fundamental Research Funds for the Central Universities,China
文摘A new technique for the analysis of the three-dimensional collapse failure mechanism and the ground surface settlements for the large-diameter shield tunnels were presented.The technique is based on a velocity field model using more different truncated solid conical blocks to clarify the multiblock failure mechanism.Furthermore,the shape of blocks between the failure surface and the tunnel face was considered as an entire circle,and the supporting pressure was assumed as non-uniform distribution on the tunnel face and increased with the tunnel embedded depth.The ground surface settlements and failure mechanism above large-diameter shield tunnels were also investigated under different supporting pressures by the finite difference method.
基金Project(51978068) supported by the National Natural Science Foundation of ChinaProject(2018YFE0103800) supported by the National Key R&D Program of China+1 种基金Project(2017M620434) supported by the China Postdoctoral Science FoundationProject(310821173501) support by the Special Fund for Basic Scientific Research of Central College of Chang’an University, China。
文摘In order to analyze the effects of backfill materials, geometries and slab setting on the settlement of bridge approach embankment, scale model was built based on the structural characteristics of bridge approach embankment, and scale model tests were carried out under different conditions. The results show that when graded gravels were selected as the backfill materials, the effect of setting approach slab to reduce the differential settlement is more prominent. When lime soils were selected as the backfill material, approach slab can moderate the longitudinal settlement slope. When using different backfill materials, the ultimate settlement of the positive trapezoidal backfill geometries is less than that of the inverted trapezoid, and the backfill geometries have little effect on the settlement slope.
基金Projects(51208071,51108312) supported by the National Natural Science Foundation of China
文摘Top structure and basement will confront the risk of being damaged on account of large stress and strain fields incurred by differential uplift and settlement between inner column and diaphragm wall in top-down method. Top-down excavation of the Metro Line 10 in Shanghai was modeled with finite element analysis software ABAQUS and parameters of subsoil were obtained by inverse analysis. Based on the finite element model and parameters, changes in the following factors were made to find more effective methods to restrain differential uplift and settlement: length of diaphragm wall, thickness of jet-grouting reinforcement layer, ways of subsoil reinforcement, sequence of pit excavation, connection between slabs and diaphragm wall or column and width of pit. Several significant results are acquired. The longer the diaphragm wall is, the greater the differential uplift between column and diaphragm wall is. Rigidity of roof slab is in general not strong enough to keep diaphragm wall and column undergoing the same uplift during excavation; Uplift at head of column and differential uplift between column and diaphragm wall decrease when subsoil from-16.6 to-43 m in pit is reinforced through jet-grouting. But, as excavation proceeds to a lower level, benefit from soil reinforcement diminishes. During the process applying vertical load, the larger the depth of diaphragm wall is, the smaller the settlement is at head of column and diaphragm wall, and the greater the differential settlement is between column and diaphragm wall. When friction connection is implemented between column, diaphragm wall and floor slabs, uplifts at head of column and diaphragm wall are larger than those of the case when tie connection is implemented, and so does differential uplift between column and diaphragm wall. The maximum deflection of diaphragm wall decreases by 58% on account of soil reinforcement in pit. The maximum deflection of diaphragm wall decreases by 61.2% when friction connection is implemented instead of tie connection.
基金Project(50879077) supported by the National Natural Science Foundation of China
文摘A new approach is proposed to analyze the settlement behavior for single pile embedded in layered soils. Firstly, soil layers surrounding pile shaft are simulated by using distributed Voigt model, and finite soil layers under the pile end are assumed to be virtual soil-pile whose cross-section area is the same as that of the pile shaft. Then, by means of Laplace transform and impedance function transfer method to solve the static equilibrium equation of pile, the analytical solution of the displacement impedance fimction at the pile head is derived. Furthermore, the analytical solution of the settlement at the head of single pile is theoretically derived by virtue of convolution theorem. Based on these solutions, the influences of parameters of soil-pile system on the settlement behavior for single pile are analyzed. Also, comparison of the load-settlement response for two well-instrumented field tests in multilayered soils is given to demonstrate the effectiveness and accuracy of the proposed approach. It can be noted that the presented solution can be used to calculate the settlement of single pile for the preliminary design of pile foundation.
基金Project(51378510) supported by the National Natural Science Foundation of ChinaProject(2017zzts157) supported by the Innovation Foundation for Postgraduate of Central South University,China
文摘The purpose of this work is to predict the state of collapse in shallow tunnel in layered strata by using a new curved failure mechanism within the framework of upper bound theorem.Particular emphasis is first given to consider the effects of seepage forces and surface settlement.Furthermore,the Hoek-Brown nonlinear failure criterion is adopted to analyze the influence of different factors on the collapsing shape.Two different curve functions which describe two different rock layers are obtained by virtual work equations under the variational principle.According to the numerical results,the parameter B in Hoek-Brown failure criterion and the unit weights in different rock layers have a positive relationship with the size of collapsing block while pore pressure coefficient and the parameter A in Hoek-Brown failure criterion present a reverse tend.
基金Project(2012QNZT050)supported by the Special Fund for Basic Scientific Research of Central Colleges,ChinaProjects(51208518,U1361204,51208519,51108464)supported by the National Natural Science Foundation of China+1 种基金Project supported by the Postdoctoral Foundation of Central South University,ChinaProjects(2013RS4030,2012RS4002)sponsored by Hunan Postdoctoral Scientific Program,China
文摘The process and characteristics of loading on high-speed railway bridge pile foundation were firstly obtained by means of field research and analysis,and the corresponding loading function was presented.One-dimensional consolidation equation of elastic multilayered soils was then established with single drainage or double drainages under multilevel loading.Moreover,the formulas for calculating effective stress and settlement were derived from the Laplace numerical inversion transform.The three-dimensional composite analysis method of bridge pile group was improved,where the actual load conditions of pile foundation could be simulated,and the consolidation characteristics of soil layers beneath pile were also taken into account.Eventually,a corresponding program named LTPGS was developed to improve the calculation efficiency.The comparison between long-term settlement obtained from the proposed method and the in-situ measurements of pile foundation was illustrated,and a close agreement is obtained.The error between computed and measured results is less than 1 mm,and it gradually reduces with time.It is shown that the proposed method can effectively simulate the long-term settlement of pile foundation and program LTPGS can provide a reliable estimation.
基金Project(2013CB036004)supported by the National Basic Research Program of ChinaProjects(51178468,51378510)supported by the National Natural Science Foundation of China
文摘The proliferation of Hoek-Brown nonlinear failure criterion and upper bound theorem makes it possible to evaluate the stability of circular tunnels with an original curved collapsing mechanism. The arch effect of shallow circle tunnel is not taken into consideration so that the mechanical characteristics can be easily described. Based on the mechanism, the upper bound solution of supporting pressure of tunnels under the condition of surface settlements and overloads on the ground surface is derived. The objective function is formed from virtual work equations under the variational principle, and solutions are presented by the optimum theory. Comparisons with previous works are made. The numerical results of the present method show great agreement with those of existing ones. With regard to the surface settlement and overloads, the influence of different rock parameters on the collapsing shape is analyzed.
基金Project (50378036) supported by the National Natural Science Foundation of China
文摘The mechanism of long-short composite piled raft foundation was discussed. Assuming the relationship between shear stress and shear strain of the surrounding soil was elasto-plastic, shear displacement method was employed to establish the different explicit relational equations between the load and the displacement at the top of pile in either elastic or elasto-plastic period. Then Mylonakis & Gazetas model was introduced to simulate the interaction between two piles or between piles and soil. Considering the effect of cushion, the flexible coefficients of interaction were provided, With the addition of a relevant program, the settlement calculation for long-short composite piled raft foundation was developed which could be used to account for the interaction of piles, soil and cushion. Finally, the calculation method was used to analyze an engineering example. The calculated value of settlement is 10.2 ram, which is close to the observed value 8.8 mm.
基金Project(2017zzts157)supported by the Innovation Foundation for Postgraduate of Central South University,China
文摘Limit analysis of the stability of geomechanical projects is one of the most difficult problems.This work investigates the influences of different parameters in NL failure strength on possible collapsing block shapes of single and twin shallow tunnels with considering the effects of surface settlement.Upper bound solutions derived by functional catastrophe theory are used for describing the distinct characteristics of falling blocks of different parts in twin tunnels.Furthermore the analytical solutions of minimum supporting pressures in shallow tunnels are obtained by the help of the variational principle.Lastly,the comparisons are made both in collapsed mechanism and stability factor with different methods.According to the numerical results in this work,the influences of different parameters on the size of collapsing block are presented in the tables and the limit supporting loads are illustrated in the form graphs that account for the surface settlement.
基金Project(50490274) supported by the National Natural Science Foundation of ChinaProject(06JJ4062) supported by the Hunan Provincial Natural Science Foundation, China
文摘In order to investigate the influence of complex conditions of in-situ surrounding rocks on the settlement behavior of nubbly coal mine waste subjected to high gravity pressure,four kinds of loading chambers made of different similar materials with different elastic moduli in experiments were used to simulate the deformation features of in-site rocks,including soft,moderate hardness,hard and extra-hard rocks. The results show that all the settlement-axial load (or axial strain-stress) curves obtained under four different surrounding rock conditions present power-exponential function feature. The final settlement of coal mine waste under the same axial load is closely related to the lumpiness gradations and the deformation behavior of chamber materials used to simulate behaviors of different in-situ surrounding rocks. In the same surrounding rock condition,the final settlement under the same maximum axial load decreases with the decrease of the proportion of larger gradation of coal mine waste. While for the same lumpiness gradation case,the settlement increases with the decrease of elastic modulus of simulated surrounding rocks and the lateral pressure induced by axial load increases with the increase of elastic modulus of loading chambers that are used to simulate different surrounding rocks. The test results also reveal that both the compaction curve and lateral pressure curve show a three-stage behavior,and the duration of each stage,which is closely related to gradations and the deformation feature of loading chamber materials,decreases with the increase of the proportion of the small size of coal mine waste and elastic modulus of the simulated rock materials.
文摘This study aims to predict ground surface settlement due to shallow tunneling and introduce the most affecting parameters on this phenomenon.Based on data collected from Shanghai LRT Line 2 project undertaken by TBM-EPB method,this research has considered the tunnel's geometric,strength,and operational factors as the dependent variables.At first,multiple regression(MR) method was used to propose equations based on various parameters.The results indicated the dependency of surface settlement on many parameters so that the interactions among different parameters make it impossible to use MR method as it leads to equations of poor accuracy.As such,adaptive neuro-fuzzy inference system(ANFIS),was used to evaluate its capabilities in terms of predicting surface settlement.Among generated ANFIS models,the model with all input parameters considered produced the best prediction,so as its associated R^2 in the test phase was obtained to be 0.957.The equations and models in which operational factors were taken into consideration gave better prediction results indicating larger relative effect of such factors.For sensitivity analysis of ANFIS model,cosine amplitude method(CAM) was employed; among other dependent variables,fill factor of grouting(n) and grouting pressure(P) were identified as the most affecting parameters.
基金Project(41202220)supported by the National Natural Science Foundation of ChinaProject(20120022120003)supported by the Research Fund for the Doctoral Program of Higher Education,China+1 种基金Project(2652012065)supported by the Fundamental Research Funds for the Central Universities of ChinaProject(2013006)supported by the Research Fund for Key Laboratory on Deep GeoDrilling Technology from the Ministry of Land and Resources of China
文摘An analysis of the stability of large-diameter circular tunnels and ground settlement during tunnelling by a pressurized shield was presented. An innovative three-dimensional translational multi-block failure mechanism was proposed to determine the face support pressure of large-shield tunnelling. Compared with the currently available mechanisms, the proposed mechanism has two unique features:(1) the supporting pressure applied to the tunnel face is assumed to have a non-uniform rather than uniform distribution, and(2) the method takes into account the entire circular excavation face instead of merely an inscribed ellipse. Based on the discrete element method, a numerical simulation of the Shanghai Yangtze River Tunnel was carried out using the Particle Flow Code in two dimensions. The immediate ground movement during excavation, as well as the behaviour of the excavation face, the shield movement, and the excavated area, was considered before modelling the excavation process.
基金Project(SWJT11ZT04)supported by the Central College Foundation of ChinaProject(2008g032-A)supported by the Major Projects S&T Foundation of China’s Ministry of Railways,China
文摘A new measurement technique is used to determine the settlement of bridge pile foundation and the thickness of deep compressed soft layer. The finite element Plaxis 3D foundation program is used in the analysis with a proposed empirical equation to modify the input parameters represented by the soil compression modulus. The results of the numerical analysis using the proposed empirical equation provide insight to the settlement analysis of pile groups in soft clayey soils; consequently, the finite element Plaxis 3D program can be a useful tool for numerical analysis. The numerical analysis is modified by adjusting the calculation of compression modulus from those obtained under pressure between 100-200 kPa by which the results of the settlement are modified and thus matching the realistic measurements. The absolute error is 3 mm which is accepted compared with the last researches. This scenario can be applied for the similar problems in the theoretical applications of deep foundations.