期刊文献+

高层建筑旋挖灌注桩支护施工技术分析 被引量:4

Construction Technology of Rotary Excavation Pile Support for High-rise Buildings
在线阅读 下载PDF
导出
摘要 高层建筑支护桩施工受施工环境、施工设备等因素影响,难以保障成桩质量。文中提出了高层建筑旋挖灌注桩支护施工技术,采用旋挖钻机钻进成孔,在孔内下放钢筋笼,通过导管向钢筋笼内灌注混凝土形成支护桩,完成高层建筑旋挖灌注桩支护施工。结果表明,设计施工技术下的灌注支护桩最大沉降量为23.47 mm,小于设计要求值,成桩质量良好。 The construction of high-rise building supporting pile is affected by the construction environment,construction equipment and other factors,so it is difficult to guarantee the quality of pile,so the construction technology of rotary excavation pile support of high-rise building is proposed.The rotary drilling rig is used to drill the hole,the steel cage is placed in the hole,and the concrete is poured into the steel cage through the pipe to form the supporting pile to complete the rotary excavation pile supporting construction of high-rise building.The results show that the maximum settlement of the perfusion support pile under the design and construction technology is 23.47mm,which is less than the design required value,and the pile formation quality is good.
作者 黎国政 Li Guozheng(Guangzhou Design Institute Group Co.Ltd.,Guangzhou,Guangdong 510620)
出处 《江西建材》 2023年第8期274-276,共3页 Jiangxi Building Materials
关键词 高层建筑 旋挖灌注桩 支护技术 施工技术 High-rise building Rotary excavation pile Support technology Construction technology
作者简介 黎国政(1995-),男,广西梧州人,本科,助理工程师,主要研究方向为工程与设计管理。
  • 相关文献

参考文献7

二级参考文献39

共引文献43

同被引文献29

引证文献4

二级引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部